Back
  Visakhapatnam   Vijayawada   Tirupati
  Target Status   Target Status   Target Status
Issue of EoI   Feb-15 completed On time   Feb-15 completed On time   Feb-15 completed On time
Last date of EoIsubmission   Mar-’15 completed On time   Mar-15 completed On time   Mar-15 completed On time
Development of Bid Documents   Apr-15 completed On time   Apr-15 completed On time   Apr-15 completed On time
Preparation of financial model   Apr-15 completed On time   Apr-15 completed On time   Jul-15 completed On time
Preparation of Project Structure   May-15 completed On time   May-15 completed On time   Aug-15 completed On time
Submission of RFQ cum RFP to INCAP   May-15 completed On time   May-15 completed On time   Sep-15 completed On time
TC, EC, APIA and GovtApproval   Aug-15 completed On time   Aug-15 completed On time   Jan-16 completed On time
BPM - Issue of RFQ cum RFP   Sep-15 completed On time   Sep-15 completed On time   Dec-16 --- ---
BPM - Submission of bid documents   Jul-16 --- ---   Jul-16 --- ---   Feb-17 --- ---
BPM - Evaluation & Shortlisting of Applicants   Jul-16 --- ---   Jul-16 --- ---   May-17 --- ---
BPM - APIA Approval   Jul-16 --- ---   Jul-16 --- ---   May-17 --- ---
BPM - Government Approval of Evaluation   Sep-16 --- ---   Sep-16 --- ---   Jun-17 --- ---
Award of contract   Aug-16 --- ---   Aug-16 --- ---   Jul-17 --- ---
Signing of Concession Agreement   Nov-16 --- ---   Nov-16 --- ---   Aug-17 --- ---
Financial Closure   Mar-17 --- ---   Mar-17 --- ---   Feb-18 --- ---
Commencement of Work   Apr-17 --- ---   Apr-17 --- ---   Mar-18 --- ---
COD   Apr-20 --- ---   Apr-20 --- ---   Apr-21 --- ---
Completed Delayed