Back
  Bhogapuram Airport   Dagadarthi Airport   Orvakallu Airport
  Target Status   Target Status   Target Status
Preparation of bid documents   1-Jun-16 Completed 18-Jun-16 Delayed by 18 days   10-Jan-16 Completed 10-Jan-16 Completed on time   10-Jul-16 Projected 10-Jul-16 Completed on time
Preparation of TEFR   10-May-16 Completed 26-May-16 Delayed by 15 days   30-Dec-15 Completed 26-Dec-15 Completed on time   30-Dec-15 Completed 26-Dec-15 Completed on time
Approval of bid documents by GoAP   2-Dec-16 2-Dec-16 On track   20-Jan-16 Completed 20-Jan-16 Completed on time   Not Applicable
Land Acquisition   31-Aug-16 Projected 31-Aug-16 Delayed by 60 days   31-Aug-16 Projected 30-Oct-16 Delayed by 60 days   31-Aug-16 Projected 30-Jul-16 Delayed by 60 days
Pre-development activities in site   31-Dec-16 Projected 31-Mar-17 On track   31-Dec-16 Projected 31-Dec-16 On track   31-Dec-16 Projected 31-Dec-16 On track
Bid submission   22-Sep-16 20 Dec 16 First pre-bid meeting held on 10th Aug'16, Second pre bid meeting scheduled for 7th Oct'16

Bid submission date for BIACL is 20th Dec' 16
  14-Mar-16 Completed 07-Jun-16 Delayed by 85 days   31-Aug-16 Projected 31-Aug-16 Last date for recieve tenders is 3rd Oct' 16
Selection of winning bidder & Issue of LOA   30-Jan-17 Projected 30-Jan-17 On track   31-Oct-16 Projected 31-Jan-17 Delayed by 3 months   30-Sep-16 Projected 30-Sep-16 Tender for the work was invited on lumpsum contract and last date to recive tenders is 03 Oct'16
MHA Clearance   31-Dec-16 Projected 31-Dec-16 On track   30-Sep-16 Projected 31-Dec-16 Delayed by 3 months   Not Applicable
Clearance by MoEF   31-Oct-16 Projected 31-Oct-16 On track   31-Aug-16 Projected 31-Aug-16 On track   31-Aug-16 Projected 31-Aug-16 EA copy forwarded Pollution Control Board, Karnool for public hearing
In principal approval by MoCA   30-Nov-16 Projected 30-Nov-16 On track   30-Sep-16 Projected 30-Sep-16 On track   30-Sep-16 Projected 30-Sep-16 On track
Financial closure by Consessionaire   30-Jun-17 Projected 31-Jun-17 On track   30-Apr-17 Projected 30-Jul-17 Delayed by 3 months   Not Applicable
Construction of airport   15-Jul-17 Projected 15-Jul-17 On track   31-May-17 Projected 30-Jul-17 Delayed by 3 months   31-Oct-16 Projected 31-Oct-16 On track
Approvals from various agencies   31-Dec-19 Projected 31-Dec-19 On track   31-Dec-17 Projected 31-Dec-17 On track   31-Dec-17 Projected 31-Dec-17 On track
Closure of existing airport at Vizag   30-Jun-20 Projected 31-Jun-20 On track   Not Applicable   Not Applicable
Completed delayed