Bhogapuram Airport |
|
Dagadarthi Airport |
|
Orvakallu Airport |
|
|
Target |
Status |
|
Target |
Status |
|
Target |
Status |
Preparation of bid documents |
|
1-Jun-16 |
Completed 18-Jun-16 |
Delayed by 18 days |
|
10-Jan-16 |
Completed 10-Jan-16 |
Completed on time |
|
10-Jul-16 |
Projected 10-Jul-16 |
Completed on time |
Preparation of TEFR |
|
10-May-16 |
Completed 26-May-16 |
Delayed by 15 days |
|
30-Dec-15 |
Completed 26-Dec-15 |
Completed on time |
|
30-Dec-15 |
Completed 26-Dec-15 |
Completed on time |
Approval of bid documents by GoAP |
|
2-Dec-16 |
2-Dec-16 |
On track |
|
20-Jan-16 |
Completed 20-Jan-16 |
Completed on time |
|
Not Applicable |
Land Acquisition |
|
31-Aug-16 |
Projected 31-Aug-16 |
Delayed by 60 days |
|
31-Aug-16 |
Projected 30-Oct-16 |
Delayed by 60 days |
|
31-Aug-16 |
Projected 30-Jul-16 |
Delayed by 60 days |
Pre-development activities in site |
|
31-Dec-16 |
Projected 31-Mar-17 |
On track |
|
31-Dec-16 |
Projected 31-Dec-16 |
On track |
|
31-Dec-16 |
Projected 31-Dec-16 |
On track |
Bid submission |
|
22-Sep-16 |
20 Dec 16 |
First pre-bid meeting held on 10th Aug'16, Second pre bid meeting scheduled for 7th Oct'16
Bid submission date for BIACL is 20th Dec' 16 |
|
14-Mar-16 |
Completed 07-Jun-16 |
Delayed by 85 days |
|
31-Aug-16 |
Projected 31-Aug-16 |
Last date for recieve tenders is 3rd Oct' 16 |
Selection of winning bidder & Issue of LOA |
|
30-Jan-17 |
Projected 30-Jan-17 |
On track |
|
31-Oct-16 |
Projected 31-Jan-17 |
Delayed by 3 months |
|
30-Sep-16 |
Projected 30-Sep-16 |
Tender for the work was invited on lumpsum contract and last date to recive tenders is 03 Oct'16 |
MHA Clearance |
|
31-Dec-16 |
Projected 31-Dec-16 |
On track |
|
30-Sep-16 |
Projected 31-Dec-16 |
Delayed by 3 months |
|
Not Applicable |
Clearance by MoEF |
|
31-Oct-16 |
Projected 31-Oct-16 |
On track |
|
31-Aug-16 |
Projected 31-Aug-16 |
On track |
|
31-Aug-16 |
Projected 31-Aug-16 |
EA copy forwarded Pollution Control Board, Karnool for public hearing |
In principal approval by MoCA |
|
30-Nov-16 |
Projected 30-Nov-16 |
On track |
|
30-Sep-16 |
Projected 30-Sep-16 |
On track |
|
30-Sep-16 |
Projected 30-Sep-16 |
On track |
Financial closure by Consessionaire |
|
30-Jun-17 |
Projected 31-Jun-17 |
On track |
|
30-Apr-17 |
Projected 30-Jul-17 |
Delayed by 3 months |
|
Not Applicable |
Construction of airport |
|
15-Jul-17 |
Projected 15-Jul-17 |
On track |
|
31-May-17 |
Projected 30-Jul-17 |
Delayed by 3 months |
|
31-Oct-16 |
Projected 31-Oct-16 |
On track |
Approvals from various agencies |
|
31-Dec-19 |
Projected 31-Dec-19 |
On track |
|
31-Dec-17 |
Projected 31-Dec-17 |
On track |
|
31-Dec-17 |
Projected 31-Dec-17 |
On track |
Closure of existing airport at Vizag |
|
30-Jun-20 |
Projected 31-Jun-20 |
On track |
|
Not Applicable |
|
Not Applicable |