  Srisailam Ring Road        
  Estimated completion date Status            
Appointment of technical consultant     Completed On time                
Preparation of TEFR/ PPR   09/16 Under progress ---                
Issue of EoI   NA --- ---                
Last date of EoI submission   NA --- ---                
Preparation of Bid Documents - Evaluation Stage                        
Preparation of financial model   Oct-16 --- ---                
Preparation of Project Structure   Oct-16 --- ---                
Submission of RFQ to INCAP   NA --- ---                
Technical Committee Approval   NA --- ---                
APIA Approval   NA --- ---                
Government Approval   NA --- ---                
Bid Process Management - Evaluation Stage                        
Issue of RFQ   NA --- ---                
Receipt of applications   NA --- ---                
Evaluation of applications - Shortlisting of Applicants for issue of RFP   NA --- ---                
Technical Committee Approval   NA --- ---                
Preparation of Bid Documents - Bid Stage                        
Submission of RFP and DCA to INCAP   Oct-16 --- ---                
Technical Committee Approval   Nov-16 --- ---                
APIA Approval   Nov-16 --- ---                
Government Approval   Nov-16 --- ---                
Bid Process Management - Bid Stage                        
Issue of RFP   Dec-16 --- ---                
Pre bid meeting   Dec-16 --- ---                
Receipt of bids   Jan-17 --- ---                
Evaluation of documents   Feb-17 --- ---                
Technical Committee Approval   Feb-17 --- ---                
Government Approval of Evaluation   Mar-17 --- ---                
Award of contract   Mar-17 --- ---                
Signing of Concession Agreement   Mar-17 --- ---                
Appointment of consultant for EIA and SIA   Apr-17 --- ---                
Appointment of Independent Engineer   Apr-17 --- ---                
Land acquisition   May-17 --- ---                
Removal of utilities   May-17 --- ---                
Submission of DPR   Jul-17 --- ---                
Environmental clearance   Jul-17 --- ---                
Financial Closure   Sep-17 --- ---                
Commencement of Work   Sep-17 --- ---                
COD   Sep-17 --- ---                
Completed Delayed