  Statement showing the activities and timelines for completion of Land Pooling for MADA      
  Minimum time Required Date of completion      
Issue of G.O. by notifying the Rules at Govt. level     11th July, 2016      
Issue of Form-I Notification by MADA   15 days 26th July, 2016      
Receipt of Objections & Suggestions from the land owners   30 days 26th Aug, 2016      
Stakeholders Meeting to explain details of the Scheme
  7 days 3rd Aug, 2016      
Disposal of objections and suggestions (Draft LPS)   15 days 11th Sept, 2016      
Notification of Finalised Area   15 days 26th Sept, 2016      
Inviting Documents from the land owners   30 days 26th Oct, 2016      
Verification of Documents   7 days 3rd Nov, 2016      
Calling for objections   15 days 18th Nov, 2016      
Field Verification & Disposal of Objections   15 days 3rd Dec, 2016      
Preparation of draft LPS   180 days 3rd June, 2017      
Calling for objections on Draft LPS   30 days 3rd July, 2017      
Preparation of final LPS   30 days 3rd Aug, 2017      
Reconstitution of plots   30 days 3rd Sept, 2017      
Allotment of plots   30 days 3rd Oct, 2017      
Issue of Land Pooling Owner Certificates (LPOC)   30 days 3rd Nov, 2017      
Completion of Infrastructure & handing over of physical possession of reconstituted plots   One Year 3rd Aug, 2018      
Completed Delayed