Statement showing the activities and timelines for completion of Land Pooling for MADA |
|
|
|
|
|
Minimum time Required |
Date of completion |
|
|
|
Issue of G.O. by notifying the Rules at Govt. level |
|
|
11th July, 2016 |
|
|
|
Issue of Form-I Notification by MADA |
|
15 days |
26th July, 2016 |
|
|
|
Receipt of Objections & Suggestions from the land owners |
|
30 days |
26th Aug, 2016 |
|
|
|
Stakeholders Meeting to explain details of the Scheme
|
|
7 days |
3rd Aug, 2016 |
|
|
|
Disposal of objections and suggestions (Draft LPS) |
|
15 days |
11th Sept, 2016 |
|
|
|
Notification of Finalised Area |
|
15 days |
26th Sept, 2016 |
|
|
|
Inviting Documents from the land owners |
|
30 days |
26th Oct, 2016 |
|
|
|
Verification of Documents |
|
7 days |
3rd Nov, 2016 |
|
|
|
Calling for objections |
|
15 days |
18th Nov, 2016 |
|
|
|
Field Verification & Disposal of Objections |
|
15 days |
3rd Dec, 2016 |
|
|
|
Preparation of draft LPS |
|
180 days |
3rd June, 2017 |
|
|
|
Calling for objections on Draft LPS |
|
30 days |
3rd July, 2017 |
|
|
|
Preparation of final LPS |
|
30 days |
3rd Aug, 2017 |
|
|
|
Reconstitution of plots |
|
30 days |
3rd Sept, 2017 |
|
|
|
Allotment of plots |
|
30 days |
3rd Oct, 2017 |
|
|
|
Issue of Land Pooling Owner Certificates (LPOC) |
|
30 days |
3rd Nov, 2017 |
|
|
|
Completion of Infrastructure & handing over of physical possession of reconstituted plots |
|
One Year |
3rd Aug, 2018 |
|
|
|